The order bagged from Adani Power includes supply of equipment (boiler, turbine, generator) and supervision of erection & commissioning for 2x800 MW power project based on supercritical technology at Raipur, Chhattisgarh.
The boiler and turbine generator are to be manufactured at BHEL’s Trichy and Haridwar plants respectively. The Unit 1 of the contract is to be supplied in 35 months and Unit 2 to be supplied 41 months. The cost of the project is more than Rs 3,500 crore.
Further, the firm won another order from Mirzapur Thermal Energy which constitutes supply of equipment (boiler, turbine, generator) and supervision of erection & commissioning for 2x800 MW power project based on supercritical technology at Mirzapur, Uttar Pradesh.
The boiler and turbine generator are to ...